Front End Change is Required When Designing for Constructability

By: Walter J. Boyce

INTRODUCTION
Change is absolutely essential for progress. Without change we keep building the same old things to the same old standards, which is the very definition of No Progress. The change must be at the front-end of the project, during the conception phase. Changes after the conception phase and during the execution phase will be disruptive rather than constructive to the project. Open minds are also essential for change; closed minds do not accept change. An open mind found that the world is round; the closed minds said he's going to fall off the edge of the world. Change also requires a strong project management team with a project manager that has an executive role.

"Project management and brain surgeons should not be selected on the basis of the lowest bid."
- Author Unknown

The executive role of the project manager is also essential, as a project manager (so called) in a monitoring role cannot make exceptions to the old corporate standards, even when substantial savings could be realized. Change should not compromise quality or safety; but again, "No Change" means "No Progress."

"The executive exists to make sensible exceptions to general rules."
- Elting E. Morison

Body
Designing for Constructability is really just updating old engineering standards, specifications and procedures. Most of these were developed years ago when the building materials were expensive and manpower was less expensive. These antiquated practices are costing companies, both owners and contractors, a lot of money on every project. This money doesn't benefit either owner or contractor; it goes right down the drain. When you hear, "We've always done it this way," you can be sure of obsolescence.

"To meet the demands of the fast changing competitive scene, we must simply learn to love change as much as we have hated it in the past."
- Tom Peters

Paradigms are very hard to overcome, but change doesn't happen until we do. Some concepts of Designing for Constructability follow.

1. Straight pipe is not expensive— fittings, valves, flanges and changes in direction are.

2 Run pipeways first, not pipes — run pipeways vertically as well as horizontally.

3. Use large process nozzles for infrequent vessel entry and eliminate manways. When the process nozzle is not quite large enough, use a reducing flange.

4. Use manways and large nozzles for lifting lugs. Manways can also be used for several process connections.

5. A 24" manway costs about twice the cost of an 18" manway.

6. Try to keep equipment close to the main piperack so that additional supports are not required.

7. Try to keep all equipment connections on the side of the piperack to facilitate pipe access to the piperack.
8. Support and anchor items and piping as close to the ground as possible. Skirt mounting the vertical vessels and saddles that extend to the mat foundation for the horizontal vessels are part of this concept.

9. Low, level piperacks are less expensive — when safety permits, field installation, insulation, painting, testing and inspection are all about half the field cost of high level rack piping, which requires the use of scaffolding.

10. Piperack design can be a big factor in the cost, schedule, and layout when a major piperack is required.

11. Compressors should share lube oil and seal oil units. This concept was recommended by the operations and maintenance people of an existing plant who had four compressors with eight oil units (four seal oil and four lube oil units). The plant would not run without all of the compressors, and that meant that all eight of the oil units must also be in operation. That was a total of twelve units, any one of which would shut the complete plant down. Their recommendation was to design with one highly reliable oil unit. They had found one oil that was suitable for all the compressors and they were using the same oil in all eight units.

12. Centrifugal compressors can often be mounted on vibration insulators with no anchor bolts. This simplifies the foundation and reduces the noise of operation.

13. A furnace stack was designed with a jacket and no refractory. The jacket space was used to preheat air. Corrosion must be considered.

14. All instrumentation and gas piping was designed to go through the catwalks of a large furnace. The openings for these items were omitted from the grating drawings, and the field extra was about a half million dollars. The next project was designed to have these items next to, and not through, the catwalks.

15. Heat exchangers and also horizontal drums can be supported with saddle supports that extend down to the mat-type foundation. This eliminates the second activity of pouring two concrete piers. The supports can be further simplified by having one of the saddles designed as the rigid anchor support. The other end saddle is designed to flex and eliminates the need for slotted holes and slide plates. When trying to maximize shop fabrication, these saddles can be used to support piping, instrumentation, etc. so that when the item is set on the mat-type foundation, the field man-hours are less.

16. Small, miscellaneous custom designed platforms, ladders, and stairs are expensive, particularly curved platforms — they are estimated at 2 1/2 times the cost of rectangular platforms (on a per square foot basis).

17. The major equipment is about 25-percent of the total installed cost of a project. The remaining 75-percent is the main target area for the Designing for Constructability savings.

18. Structures, when required, should be utilized to the fullest extent possible, and minor items can be brought to that structure rather than building a new structure.

19. Small concrete piers, pads, and paving pours are expensive ($700 per yard) when compared to mass pours of about $100 per yard (today's basis).

20. Buy standard equipment using a performance type specification. Select vendor and negotiate minor changes, the delivery, and the spare parts (for years).

A study of standard specifications for a major E & C contractor found much duplicate information — and, as would be expected, where information is repeated time and again there is also conflicting information. Eliminating the duplicate information reduced the thickness of these specifications to one fourth of the original thickness. The following chart shows the equipment classifications and subjects covered. Everything below the top line of "x's" is redundant but not identical. The solution is to have a cover specification to cover all the co-on subjects once and not have them repeated in each equipment specification because that would be a big expense in duplication and confusion.

The updating of engineering, standards, specifications and procedures should follow the Ten Commandments of the KISS Philosophy:
KEEP IT STRAIGHT& SIMPLE

KEEP IT SAME SIZE

KEEP IT SHOP STANDARD

KEEP IT SQUARE & SQUATTY

KEEP IT SPECIFICATION SIMPLE

KEEP IT STANDARD SIZE

KEEP IT SUPPORT SIMPLE

KEEP IT STANDARDS SIMPLE

KEEP IT SCHEDULE SACRED

KEEP IT SUITABLE FOR SITE
Keep it Straight & Simple …
applies to many things but is most important when doing the plant layout, starting with piperacks, roads, sewers, cable trays and drainage ditches.

Layout of the equipment required for a project is a very important aspect of Designing for Constructability. Accessibility may be the best word to define layout: Access for people, equipment, piping, electrical and instrumentation. The access must consider construction, production, safety and maintenance. The layout must be finalized early in the project but is often not given the proper attention it requires. There is probably no one item that can influence the cost more than the layout.

There are many ways to make a layout. I feel that the best and fastest way is with a simple block model. No drawings are made to make the model: the model comes first, the drawings come second. A model is not only three dimensional, it also speaks all languages — not just foreign languages but the languages of construction, production, safety, maintenance, etc. With the simple block model we lay out pipe racks, cable trays, drainage ditches, roads and buildings first; then place equipment. This will make a cleaner, straighter and less expensive layout. Don't locate a piece of equipment without knowing how you are going to get to it with pipe, electrical, instrumentation, etc. Don't run pipe racks and roads side by side as this will sterilize one side of the rack as far as equipment placement is concerned. This will often force spur pipe racks to be required, which in turn require at least two bore pipe fittings and additional pipe to reach the equipment. This also adds to the total length of pipe rack required, and total cost is function of length.


Keep it Same Size …
includes things like heat exchanger tubes and support spacing, vessel manways and instrument connections, pipe rack supports, building bays, control valves and block valves, windows, doors, etc.

Keep It Shop Standard …

is a big factor of cost. When supplier is asked to deviate from his standard, it will cost more. It will be a custom order; it will probably take longer and it may carry lesser guarantee since it is not his proven standard. He is not likely to tell his client this as he is bending over backwards to satisfy.

Keep It Square & Squatty …
applies to many things, including buildings, as a square building is less cost per square foot than T-shaped or L-shaped building. The "Squatty" is to stress the cost of building structures and equipment higher than necessary. This is even more important in earthquake areas.

How high does the structure really need to be? NPSH requirements are, of course, a real concern — but contingencies on top of contingencies have been found to add considerable cost to structures and to the whole total installed cost. The real situation may have the normal liquid level several feet above the outlet, which should be considered. The unreal custom of calculating NPSH requirements based on full design flow (plus more contingencies) at the face of the vessel outlet flange is part of the problem. A review of the above, plus other contingencies, resulted in lowering a complete process unit by l§ feet. This involved some open-minded process people.


Keep It Specification Simple …
so that the shop standard equipment can be purchased. The simple specification would be a blue Cadillac with four doors and loaded with standard Cadillac extras while a complex specification would be something like a red Honda with a Chrysler motor, a Ford transmission and a Rolls Royce radio. This sounds ridiculous, but a lot of companies are buying this type of equipment. Again, the vendor is not likely to tell his client about this as he is trying to satisfy.

Keep It Standard Size …
applies to many items. Foundations and concrete structures can be designed to fit standard size forms. Vessels can often be designed to fit standard size steel plates. Standard size vessels can often be bought from a catalogue. These are pre-engineered and generally involve less cost and quick delivery. They can be purchased with jackets, agitators, etc. Standard size for a project need not be an industry standard. The project can set its own standards for many things to simplify constructability, such as manway size, instrument supports, handrails, stairs, ladders, anchor bolts, etc.

Keep It Support Simple …
which starts with a mat-type foundation for a process unit. As many items as possible are designed to sit on the mat. Vertical drums are preferred as they require less space and can be skirt or leg mounted on the mat without the additional activity of piers, etc. Vertical reboilers can also be on legs. Inline pumps are much simpler to support and are less total installed cost. Heat exchangers and horizontal drums can be designed with one support rigid and one support flexible in lieu of slotted holes and slide plates. The pipe rack design concept (which follows) makes a lot of custom supports unnecessary.

Keep It Schedule Sacred …
as the financing, payback and product sales contracts are all based on the start-up date. The schedule must be realistic and Designing for Constructability should shorten the schedule. Once a realistic schedule is developed, stay with it and do what is necessary to make it happen.

Keep It Suitable For Site …
location, as local conditions change as to wind, sun, rain, temperature, labor supply, customs, available materials and equipment. These factors should have an impact on the design, procurement and construction approach.

Keep It Standards Simple …
is the real key to Designing for Constructability. Concepts for standardized pipe racks, stairs, handrails, storage tanks, compressor structures, access platforms, block valves, flare headers, cooling tower and control building design follow.

Pipe Racks …
are a major item in most process plant projects. They are substantial structures and often fireproofed. They can also be used to support some equipment that requires elevation. This concept is based on a precast concrete rack design which is wider, but with outriggers to minimize span and with a precast concrete deck on top. This design may require more ground area but gives an equal amount of prime space on top of the deck right in the center of the process. In theory (and in fact) this has shortened the overall length of the rack layout by one-third, because in addition to the two sides of the rack, we can now use three sides of the rack, including the top.

This pipe rack concept has many advantages:
1. Cost and schedule are both improved.

2. Gives a liberal maintenance access way under the center of the pipe rack between the support columns, ±14 feet heath.

3. Outside of the support columns the outriggers give extra rack space and uses space down to ±8 feet high.

4. The top precast deck gives weather protection and improved productivity for construction, production and maintenance.

5. The deck is also a firebreak between the piping and the equipment on top.

6. With this wide area of access, exchanger bundles can be pulled into this covered area. With the dirty end of exchangers towards the pipe rack, the piping is shortened and the oily water sewer is in a straight line.

7. The precast deck can be used for many elevated items. This has also eliminated many structures alongside of racks, which also impede access to the rack. The piping to items on top of the deck are generally shorter.

8. The deck which covers the full width and length of the rack in the process area also serves to support any pipe entering or leaving the rack, by rod hangers.

9. The deck also serves for access to control valve stations and often shortens the piping which would otherwise go down to grade and up again. Relief valve stations are also mounted on this deck; and with the flare header Just below the deck, the relief valve discharge piping is short.

Stairs …
fabrication is greatly simplified. When all operating and maintenance floors, platforms, catwalks, stairway landings, etc. are established at L-we-foot increments, it will make all stairways the same angle with 8" risers and 10" treads. Three risers and two ladder rungs will equal two feet. The two foot increments must apply to the top of the walking surfaces. This not only makes the stair stringers the same angle, but also the handrails, etc. It simplifies design, fabrication and construction.

Handrail …
fabrication is simplified with standard bays, and handrail design can also be simplified compared to many standards. One design, which was used to simplify field fabrication made necessary by local labor requirements, proved to be very cost effective. This design was further simplified by having all operating levels on the two-foot increments, as discussed above, so that all stairway handrails were the same angle, then standard bays can be utilized, 20-foot bays would have two ±9'-2' sections and 24-foot bays would have three 7'-4" sections.

Compressor Structures …
requiring cranes can be designed with an "A" frame type crane supported on the concrete tabletop which supports the compressor. This will make a second structure to support a bridge crane unnecessary. Cantilevered extensions from the tabletop will support precast concrete decking on both sides of the compressors. A pre-engineered building can be added to the tabletop to give weather protection.

Storage Tanks …
can often use standard plates to minimize cutting and waste. A tank fabricator required a very high cancellation fee when tanks were canceled because he had cut the plates and considered them to be of little value. It seems that standard tanks are not even-feet in diameter but even-feet in circumference. His plates were 84 inches by 240 inches, or 7 feet by 20 feet. His standard tanks had diameters of 6.37 feet (one plate), 12.74 feet (two places), 19.1 feet (three plates), etc.


Access Platforms …
are determined to a great extent by nozzle locations. Random nozzle orientation can be very costly. One project found that planned orientation of nozzles reduced the amount of platform required by about half. The contractor on that project had a factor of 2h times the cost of rectangular for the cost of circular ones. With the planned orientation of nozzles, most of the platforms were rectangular. Each vessel needs to be reviewed by open-minded process, piping and vessel people to accomplish these substantial savings.

Block Valve Sizing …
for control valves, pumps, traps and relief valves can not only be a very big dollar item, but also a substantial manpower factor.

Control valve stations can be treated as a sub-assembly. They can be shipped complete with the control valve positioned above its working position held in place by through bolts which also hold a straight piece of pipe between the matching flanges of the block valves. The straight piece of pipe (no flanges) is used for flushing and testing, then discarded and the control valve lowered into place.

To make this concept work there two sizes required: the line size and the control valve body size. The line size is usually the first to be known and often the block valves are ordered on this basis. This practice can be very costly, particularly when the control valve body size is more than one size smaller than the line size. The trim size of the control valve can be known later. Once the two sizes are known, the block valves, the bypass valve, the reducing ells and the flanges can be purchased. The valve bodies will all be the same size. The control valve will have trim with an orifice about 2/3 to 3/4 of the valve body size. This gives an area of about half the cross section of a full port block valve of the same body size. (One client called the pressure drop through the block valves negligible after their computer check.) In addition to saving valve costs, there are additional savings in the field installation ape— and gear operators can often be eliminated with a smaller block valve size. The bypass valves could be sized based on the control valve trim capacity; this would usually be a smaller body size than the control valve size.


This concept requires only half the welds of the standards which call for block valves to be smaller than line size, but bigger than control valve body size. Notice that reducing cells are used to go from line size to valve body size. Buying an ell and a reducer in lieu of one reducing ell and then making three welds in lieu of two welds is not Designing for Constructability.


FLARE HEADERS ...

are often designed with supports spaced every 20 feet and a conventional, narrow rack with two footers -and two vertical supports. Designing for Constructability has utilized the structural strength of the flare header to support the small lines and conduits or cable tray every 20 feet, but the flare header supports can be much farther apart. Designs have used 60-foot spacing for 36" headers and 100-foot spacing for 72-inch headers. This reduces the number of footers and structural columns to one-sixth or one-tenth the number required at 20-foot spacing. These items will be bigger but should require a lot less cost and time.

COOLING TOWER ...
piping is simplified when basin and pumps are on a common mat foundation. When the pump suction lines are short they should not require a size any bigger than the pump suction size. The pump basin can be Just an extension of the tower basin. When the screens are installed at an angle, the extension is minimal. Man-hours in forming can be minimized when concrete piers are eliminated in lieu of longer columns of the cooling tower structure; also man-hours can be saved by making the mat foundation thicker and all in one piece. When the basin and pumps are on a common at-type foundation and there can be no differential settlement, then expensive expansion Joints in the pump suction piping can be eliminated.



CONTROL BUILDING DESIGN ...
can be simplified to reduce both man-hours and cost. Some of the concepts to look at for simplification follows.

The instrument racks can be connected and fed from the top in lieu of the bottom. This eliminates the need for the computer floor in the rack room and shortens the wiring as they enter the building near the top of the racks.

The control room is located directly above the rack room. This eliminates the need for the computer floor in the control room as penetrations can be made in the floor where required. Again this shortens the wiring.

The ground floor would have, in addition to the rack room, the locker rooms and the main toilet facilities, the mechanical room and switch gear room.

The second floor would have the cleaner functions. In addition to the control room there would be the offices, the laboratory, conference room and more toilets. There are both advantages and disadvantages of this second story concept. I feel that the main advantages are the smaller foundation, simplified air conditioning and simplified construction.

Simplified construction of this building can reduce field man-hours substantially. The use of precast double "TT's" for second floor, roof and exterior walls makes for fast low-cost shell. This is an acceptable "blast resistant" building. This type of construction can also eliminate the false ceilings and simplify the lighting and air conditioning. I call this "parking garage construction".

Lighting is by fluorescent single bulb units mounted directly on the underside of the double "TT decking". This also covers most of the Joint between the sections of decking. The conduit and Junction boxes are on the top side of the double "TT's" and then buried in the lightweight concrete floor and roof. The telephone conduits are also buried like this. The junction boxes are flush with the finished floor and accessible.

Air conditioning ducts are large rectangular soffit-type design. They may be on one wall or all four walls, depending on the size of the rooms. The distribution is controlled by outlet dampers rather than duct size. One client opted for thermostat controlled dampers so that two offices side-by-side could have several degrees differential to suit the comfort of individuals.

A Middle East project had 12 air conditioning units in as many areas throughout the complex. They also used a substantial amount of chilled water in the processes. We had three 50% chilled water units from which we used chilled water as a utility to air handling units at the 12 locations. This not only eliminated the 12 A.C. compressors, but also the noise in office-type areas and the maintenance of the compressors.