|

 |
Project Capital Savings
Contracting Strategies through Experienced Owner Management
By: Robert A. King and Robert J.
Hesse and Robert A. King, Inc. (RAKI), Houston
Every LNG facility is built to make the same product,
!!MONEY!! Though owners' business managers know
this, too often the message gets lost when responsibility
is delegated, or sometimes abdicated, to those who are
not stakeholders in the bottom line. It is initially
entrusted to the Owner Project Management (OPM) team
and later, during a critical step, to the engineering,
procurement, and construction (EPC) contractor. This
article focuses on the decisions by people concerned
with achieving better financial return on the money
invested in LNG facilities, including liquefaction plants,
export and import terminals, and pipeline systems. First
we introduce just a few technical and management topics
that demonstrate the potential to save money and reduce
losses on LNG facilities. This money then becomes the
incentive to examine the role of OPM and the effective
strategies for contracting the project work. The emphasis
is on maximizing the use of assets and reducing the
project time. Industry case examples, including a variety
of LNG facilities, are shown in italics with money adjusted
for inflation to 1998 US dollars. Obviously company
identities must remain anonymous.
COST SAVINGS
The Total Installed Cost (TIC) for an LNG plant is typically
distributed as follows: 3% OPM; 12% - Engineering; 50%
- Equipment & Materials; 35% - Construction. Hence,
what is described here as "Designing For Constructability"
(DFC) is an essential element in reducing the capital
cost. DFC is a form of value engineering in which the
TIC is evaluated vis-a-vis all EPC steps, but especially
material and construction. This review is conducted
by field experienced engineers and usually reduces TIC
by simplified, proven design criteria and techniques.
Through the proper application of DFC, potential savings
of more than 10% of the TIC is not unusual. There
were two contemporary projects at different locations
but of equal capacity, with the same owner, contractor,
and licensor. The final TIC of one using DFC cost 30%
less than the other without DFC.
When contractors estimate TIC they do a "take-off"
i.e. count, of all bulk material, much of which is piping
and valves. These numbers, together with local labor
productivity and manhour rates, then become multiplicative
factors in estimating the construction labor costs.
The "take-off' numbers are significant because
of their cumulative impact on the TIC since they contribute
to defining both material and labor costs. The drawing
that most affects piping and thus TIC is the Plot Plan.
Many Plot Plans are analogous to the boxed grid of a
low profile, rural town rather than the more radial
pattern of a high-rise city. In a plant, the latter
fundamentally reduces the "take-off" quantities
by reducing piping distances between equipment. Keeping
this in mind, we will describe two examples of ways
effective OPM can significantly reduce material and
equipment in order to dramatically lower capital costs.
In soma cases such ideas are dependent on local field
labor conditions. One example is large and one small
but both are significant. These cost savings ideas
were only a few recently considered for two large base
load LNG plants, one of which is currently under construction.
It was estimated that a 10% saving off the final TIC
would be realized in each case.
(Click to enlarge.)
STACKED EQUIPMENT LAYOUT - Major lengths of large
diameter pipe interconnect with the propane condensers
and other air coolers. Figure 1 shows the air coolers
stacked on top of a rack using quarter-point design.
This saves significant money by reducing materials,
especially piping, and by lessening the labor, particularly
to pull pipe and cable through the rack instead of laying
it on the wings of the structure. In many locations,
either field-poured, tilt-up racks or pre-cast concrete
racks can save additional money by reducing steel costs
and eliminating fire-proofing. Monolithic mat foundations
also eliminate the need for anchor bolts.
(Click to enlarge.)
BYPASS VALVE ARRANGEMENT -
The dollars are in the details! Figure 2 shows the usual
and DFC bypass valve arrangements. Not only does this
eliminate half the number of welds, but also reduces
the size of several valves. Normally, bypass and block
valves are unnecessarily sized at the same internal
diameter as the line. A valve twice as large often costs
four times as much. This seemingly insignificant concept
can save a sizable amount of money on a world scale
plant, particularly on stainless steel. On one plant,
over US $10 million was saved on carbon steel alone
by utilizing DFC bypass valve design.
POTENTIAL OVERRUNS
The corollary to potential cost savings is cost overrun,
which is a major concern: both the cost of capital and
the capital cost can be critical to return on investment.
We estimate a cost overrun of about 7% (compounded)
per month of the TIC for schedule delays after mechanical
completion. This percentage includes the costs of capital,
management, operating labor, and loss of profit. A
major LNG plant took over 5 extra months to start-up
due to a serious problem with the performance of the
main compressor that could have been avoided by competent
OPM. This US $2.0 billion project incurred a staggering
penalty in excess of US $700 million.
OWNER MANAGEMENT
Only experienced OPM can ensure that all potential savings
are realized and cost overruns avoided. In establishing
an OPM team, the owner's management must recognize what
makes an OPM team successful, what are the challenges
staffing the team, and what are the criteria for selecting
the team members. Proven MAXIMS for successful
OPM can be summarized as follows:
MAINTAINING LEADERSHIP with hands-on, combat
experience. A formal education alone does not make a
successful leader. Managing for results is what pays-off.
A TO Z PLANNING and close the books every night.
The contracting and execution plan, including a well
defined scope of work and budget, needs to be established
early in the project. The books must be closed nightly
to manage the trends in the project by plotting them
against the original plan. If there are gaps compared
to the plan, corrective action must be taken immediately.
On one major LNG chain, to save about $5 million,
the receiving terminal tanks were designed at a low
pressure. The pressure in the shipping vessel was slightly
higher which would have caused a massive boil off during
unloading. The receiving terminal tanks had to be reordered
at an estimated penalty of over $20 million.
X-ECUTE DECISION COST CONTROL by the managers,
supported by professional, experienced cost engineers.
Timely and appropriate decisions can only be made based
on accurate and timely cost data.
IMPLEMENT ACTION REPORTING, i.e. report for action
not history. Computer technology has provided the capability
to report the same data in almost an infinite number
of ways. Throwing more money and technology at a problem
can make it more complex without getting value-added
results.
MONEY - STOP CHANGES before the start of EPC
when a large amount of money is spent. Once the basic
design is completed, changes must be stopped during
the detailed engineering phase. Many engineers' strength
of exactitude in design can be a weakness in not recognizing
the impact on cost for that extra decimal point of accuracy.
SPEED is of the essence. With the right systems,
smart people working fast can create a competitive edge.
Time is money which goes directly to the bottom line.
OPM must be an experienced, multi-disciplined team with
a proven successful track record on previous similar
EPC projects, i.e., it must meet the MAXIMS principle.
The team should be committed to deadlines. These people
must be available in a timely manner for the duration
of the project and preferably have previously worked
together. Delayed schedule due to late OPM assignment
will cost the project many times more than the 3% of
TIC they cost the project.
Most importantly, OPM must be independent, having no
conflict of interest by either being another owner or
a contractor or associated with them. A consortium owner
partner is not, "de facto", independent. On
one LNG project, the managing partner also owned part
of the local utility so was not interested in on-site
cogeneration of power even though it would have benefited
the other owner partners. Also contractors cannot effectively
manage their competitors. On another $1.4 ion project,
the managing contractor and execution contractor were
both major E&C firms. The managing contractor convinced
the owner that the execution contractor wes not performing
satisfactorily. The owner was persuaded to switch the
contractors' roles. Human nature combined with financial
incentive dictated that the managing contractor was
not working in the best interest of the owner but in
its own best interest since the EPC contract afforded
more profit potential. The client incurred an approximate
penalty of over US $150 million due to the discord and
discontinuity.
Many owners may not be able to staff the OPM team internally.
Staffing problems may be due to a number of factors.
The owner may lack the experienced people since few
base load LNG facilities have been built since the 1970s.
International assignments may cause some experienced
employees, and their families, to be unwilling to live
at the site. Many staffs have been recently re-engineered,
i.e. "downsized", with little corporate interest
in hiring full time professionals for only the duration
of a temporary project. Lenders or partners may require
that they staff part or all the OPM roles themselves.
Most of these issues can be resolved by appropriately
contracting OPM services from a third party.
COST VS. CONTROL
It is clear that there is a great potential for money
to be saved or lost depending on the capabilities of
the OPM team. But how does that team control the costs?
By focusing on saving time, there is a cost reduction.
We must review the time and phases during which the
money is spent, which, for the purposes of this discussion,
we will define as follows. Though generally sequential,
these phases can overlap.
| PHASE DESCRIPTION |
CONTENTS |
| 0 FEASIBILITY PLAN |
Concept, Design Basis, Evaluation, Development, etc. |
| I BASIC ENGINEERING |
Design Criteria, Cost Parameters, Contracts Awarded, etc. |
| II DETAILED EXECUTION |
Implementation, EPC Execution, Plant Acceptance, etc. |
| III PLANT OPERATION |
Start-up, Training, Operation, Maintenance, Marketing, etc.
|
(Click to enlarge.)
The classic "S" shaped curve for a project's
capital cost versus time is shown in Figure 3. Projects
start out slowly, spending little money in Phase 0 and
I. This is the time when all goals, directions, and
decisions are established which dictate success or failure
on a project. Then during Phase II the spending enters
a steep curve when the equipment and major materials
are purchased and construction starts. Spending slows
in the field approaching Phase III start-up and operation.
The same figure contains the approximate inverse of
the cost curve which reflects the OPM's ability to control
costs for the same time period. At the beginning of
the project, the OPM team has the most ability to control
the ultimate TIC because it is at that time that they
define the scope. In the extreme case, should the project
be immediately cancelled, there is little or no cost
for the careful planning. In the other extreme, should
the project be mismanaged and not started up on time,
the project is guaranteed to overrun.
CONTRACTING OPTIONS
We now recognize that there is a potential for substantial
time and thus money to be saved and earned. We also
know that it is up to the experienced, independent OPM
team to lay the ground work to accomplish this objective
early in the project, when they have the most control.
Time management and DFC savings are examples of ensuring
such savings. But the critical step in this equation
is when the contract is let to the EPC contractor; when
the most control is lost as shown in Figure 3. There
are two fundamental contracting options available: Reimbursable,
sometimes known as Cost Plus or Time and Material (T&M),
provides for payment based on hourly rates for personnel
or unit rates for defined tasks plus non-payroll costs
such as equipment, material, and fee.
Lump Sum is sometimes known as either Fixed Price
or, if plant start-up and commensurate performance guarantees
are included, Lump Sum Turn-Key (LSTK). Lump Sum provides
for payment of an all-inclusive price for the defined
scope.
There are considerable differences between these options
that directly affect project schedules, cost and control,
payment terms, management flexibility, and other issues.
Reimbursable agreements offer the owner the greatest
flexibility to modify scope by allowing a partial overlap
of Phases I and !1. Lump sum gives the OPM the least
flexibility for late scope modifications since there
is a distinct break between Phases I and II. With flexibility
comes obligations. Reimbursable contracts require the
OPM to take greater responsibility to control costs
compared to lump sum.
(Click to enlarge.)
Reimbursable contracts offer the greatest potential
for saving the investor money! But this depends on experienced
OPM. The cost comparison of reimbursable versus lump
sum in Figure 4 does not show all possible eventualities
but will assist in the following discussions with terms
in bold. For the purpose of this comparison we will
assume that both contracting approaches start with the
same Base Estimate of TIC, are bid on a competitive
basis, and contain differences based on typical percentage
variances of the TIC. The overall result of the following
evaluation is that it is not unusual for the Revised
Estimate to yield a Final Price for a lump
sum contract that is over 10% higher than for a reimbursable
contract.
Contingency is added to the Base Estimate to
cover Design Allowance and unknowns. Design
Allowance is for undefined items, for instance small
nozzles, lifting lugs, and "take-off" errors
that historically are always present, but at a known
amount of about 5% of TIC. When combined with unknowns
that cannot be predicted, a total Contingency
of usually 10% of TIC is added to the estimate in order
to cover the risks of converting to a lump sum price.
Such price must also include the contractor's lump sum
bidding costs which are typically 0.50-0.75% of TIC.
A well managed project should not use the unknown portion
of the contingency. In that case, such unused contingency
accrues to the owner's account on Reimbursable and the
contractor's account on Lump Sum. Contingency is so
important that it is one tool for controlling the overall
project costs.
Changes to the scope almost always cause the Final
Price to be higher than the Contract Price.
Changes are often referred to as Change Orders,
especially for lump sum. They usually originate from
new owner requirements but also come from third party
requirements that were not anticipated in the contractor's
original scope. In either case, lump sum contractors
will price the positive changes at a higher rate than
negative changes. Since almost all projects have net
positive changes, the result is a cumulative higher
price for changes to a lump sum contract than to a reimbursable
contract, It is not unusual for changes to a lump sum
contract to be double those of a reimbursable contract.
Designing For Constructability (DFC) - principles are
applied more effectively under a reimbursable contract
because of the flexible relationship between OPM and
the contractor in changing scope. But the responsibility
for meaningful DFC input during Phase 0 and I
still clearly remains with the OPM team.
Schedule is key to a successful project, whether
lump sum or reimbursable. Time is of the essence; the
schedule must be fast track to reduce capital cost.
For lump sum, the contractors' bidding time is usually
3-4 months with an extra 2-3 months for a comprehensive
Request for Proposal preparation and bid evaluation
by the OPM. Phases I and II do not overlap and the overall
project schedule is extended by 4-6 months. For reimbursable,
it only takes a few weeks for the contractor to bid
its reimbursable rates and the OPM to evaluate those
bids. The benefits are more effective use of time and
improved on-time delivery of product. This directly
improves return on investment which is not shown in
Figure 4 since the amounts depend on project-specific
economics.
STRATEGY SELECTION
There are a number of issues that can affect the selection
of one contracting strategy over another. In most cases,
the arguments against taking advantage of the reimbursable
approach can be overcome.
OPM qualifications are critical to either option but
especially for reimbursable. Owners are wagering that
their OPM team can shorten schedule, implement DFC,
and manage the risk of cost overruns better than the
contractor can under a lump sum contract.
Lender requirements may dictate that the project be
lump sum to lessen risk. But the reduction in risk is
not nearly as great as many lenders think. Even if the
lump sum contractor is properly bonded, secondary costs
can have a big impact on the owner. If a contractor
is subject to contractual non-performance, the liquidated
damages it will pay will not normally exceed its profit
or about 10% of the lump sum price. This will barely
cover one to two months schedule loss after a failed
start-up. On one LNG plant, the EPC contractor could
not complete its work so the owner lost substantial
money in transferring the responsibility to another
contractor.
Schedule restraints may prevent a lump sum approach
since the contractor's bidding cycle can add as much
as 4 - 6 months to the overall project schedule. The
restraints can be caused by many factors including the
need to meet a weather window or the relative sensitivity
of the economics to early product delivery.
The qualified contractors may be flush with work. This
can cause contractors to be unwilling to either bid
lump sum or to do so at a reasonable price. Scope definition
and its level of detail, if not available early in the
project, can also demand a reimbursable contract.
Other considerations, for instance geopolitical, may
require the use of local contractors which can affect
the normal contracting strategy. Labor availability
or process expertise may dictate the need for splitting
the EPC contract between engineering/procurement and
construction. The engineering and separately the construction
may need to be further split into multiple sub-contracts.
On some occasions, OPM must pre-arrange or at least
encourage associations between contractors in order
to best meet the interests of the investors. Such splitting
of contracts lends itself to a reimbursable approach.
INCENTIVE TERMS
Incentive terms are a means of sharing revenues between
the contractor and owner in order to enhance team performance
in meeting specific objectives. Such terms become very
useful in addressing project specific requirements like
the ones just discussed or in seeking to modify the
general results outlined in Figure 4. These terms are
usually just variations of the reimbursable and lump
sum approaches and should be made quantitative wherever
possible.
GUARANTEED MAXIMUM is a reimbursable contract with a
guaranteed, not to exceed, price. A contractor will
normally estimate the "cap" as if it were
a lump sum price. So it will include contingency, some
of which may be in the contractor's reimbursable rates.
Most contractors are reluctant to contract on this basis
since they own the risk and their client owns the reward.
SHARING UNDER-/OVERRUNS from an estimated price, sometimes
called a Target Price, is a more equitable way of providing
incentive to a contractor than a guaranteed maximum.
This approach shares both the risk and reward between
the owner and contractor thus encouraging a stronger
team effort.
COST PLUS FIXED FEE, sometimes called an Omnibus Fee,
is a reimbursable contract with a lump sum fee. This
has the advantage of encouraging the contractor to finish
the work quickly since no further profit is gained if
it continues. Indeed, additional contractor profit maybe
lost should it be possible for the contractor to assign
the same professionals to other profitable projects.
BONUSES AND PENALTIES as incentives, can be applied
to either lump sum or reimbursable contracts. A combination
of such incentives is recommended since that fosters
greater cooperation between the owner and contractor.
They should be quantitative on such things as schedule,
field safety, global process guarantees, field rework,
variances from Target Price, Change Order values, implemented
DFC savings, etc. When applied to DFC, savings can accrue
even on lump sum contracts which would lower the final
price shown in Figure 4. Incentives can be qualitative
on such things as labor relations, team cooperation,
etc. but these should be at the sole discretion of OPM.
Many incentives are only effective when individuals
in the contractor's, and sometimes owner's, organizations
share in the bonuses during the course of the project.
One major revamp project used open shop construction
labor at a plant being operated by union labor. Labor
relations were critical, and a bonus program that included
the construction laborers successfully prevented potential
major losses due to work stoppage.
CONCLUSIONS
It is critical to have an experienced, independent OPM
team that defines the scope of work early while incorporating
all the latest DFC cost savings ideas. Once the EPC
contract is let, the OPM team must not allow the design
to be changed. With strong OPM the contract should preferably
be reimbursable but should have incentive terms to encourage
TIC savings even if it is lump sum. Continued OPM management
should emphasize a fast track schedule, measuring time
to control cost, with successful implementation of all
the design requirements. Prompt start-up is essential
to prevent major cost overruns.
|
|