|

 |
Design for Constructability
Proper design calls for the total integration of "quality management,"
"value engineering" and "constructability."
By: W. J. Boyce
Designing for constructability will be just a buzzword without the right
team. The team must have the right attitude, experience and authority (or
the guts to take the authority) to make things happen. It is based on the
same philosophy as the "Ten Commandments of KISS Design":
- Keep It Straight and Simple
- Keep Its Structures Simple
- Keep Its Specification Simple
- Keep It Shop Standard
- Keep Its Standards Simple
- Keep It the Same Size
- Keep It Square and Squatty
- Keep Its Support Simple
- Keep Its Schedule Sacred
- Keep It Site Suitable.
(Click to enlarge.)
Keep it straight and simple applies to many things,
but is most important during the plot-plan and layout
phase. The plot-plan phase is the general location of
units. The layout phase is a much more detailed review
of each individual piece of equipment. It includes not
only the best location of each item, but also the orientation
of each nozzle. Layouts are not just plan views, but also
include elevations and sections. Access may be the best
word to define layout. Layouts must consider access for
construction, production and maintenance. The layout must
be finalized early in the project but is often not given
the attention it requires. It is often the biggest source
of savings, but once finalized it's difficult or impossible
to change due to schedule and permits.
(Click to enlarge.)Layouts are best made with a simple block model made
by an experienced layout specialist, and not by a model
maker. No layout drawings are made to make the model.
The model comes first, the drawings come second. A model
is not only three dimensional, it also speaks all languages,
not just foreign languages but also the languages of
construction, production, safety, maintenance, etc.
Groups of people will look at, and discuss, and maybe
cuss a physical model. But groups do not conference
over a 3D CAD screen. With a simple block model we first
make a straight layout of piperacks, cable trays, drainage
trenches, sewers, flair header and roads, and then place
equipment. We never place a piece of equipment without
knowing how we can get to it with piping, electrical,
and sewers, etc. during construction, operation, and
maintenance, Do not run the pipe-racks and roads side
by side. This will sterilize one side of the rack for
equipment placement. This will often force spur piperacks
to be required, which will require more pipe, at least,
two more fittings and four more welds. Run piperacks
vertically as well as horizontally.
Keep its structures simple by using the quarter-point
design concept as shown in the typical cross section.
This design simply means getting heavy loads over the
vertical supports (Fig. 1).

(Click to enlarge.)
-
Foundation
design for structures can make a big difference
in both time and cost. Most foundations are still
designed from old standards based on cheap labor and
expensive materials, Today the opposite is true. Mass
pours of' concrete today are in the range of $100
per cubic yard, and small or complex pours approach
ten times that cost. A single-mat-type foundation
has been used to support, a complete process unit.
Larger process units often have three mats, and all
three mats are the full length of the process unit.
The center mat supports the piperack, pumps, strainers
and miscellaneous items. It has a high ridge in the
center and drains to a precast storm water trench
on each side. The trenches are used for screeds when
pouring the mats. This center mat is also an unobstructed
maintenance access way from end to end of the unit.
The other two mats are on each side and slope to the trenches. These
two mats support the major equipment such as columns, heat exchangers and
vessels. Vertical vessels are preferred. They require less space. With
skirt or leg supports, they can sit directly on the mat without the additional
activity of piers. Vertical reboilers can also be on legs. Inline pumps
are much simpler to support and are less total installed cost. Horizontal
pumps can be supported on studs drilled into the mat foundation and are
doublenutted at the pump base. Again, no concrete is required. This also
gives horizontal pump piping the same flexing and stress advantage of inline
pumps. With mat foundations there are no octangular pedestals as columns
and vertical vessels sit only on grout.
(Click to enlarge.)
-
Piperack
structure is a major item and is often fire proofed.
It is also an important cost factor. If the piperack
is 40 it wide, don't span the 40 ft. With quarter-point
design the span should be about 20 to 25 ft. This
piperack and equipment support concept is based on
precast concrete bents with a precast concrete deck
on top. I call this "parking garage" construction.
This design may require more ground area but gives
an equal amount of prime space on the deck right in
the center of the process area. This design has shortened
the overall length of the piperack and pipes and cables
by one third. With this design we now use three sides
of the rack for equipment placement in lieu of two
sides. This piperack design concept has many advantages:
- Cost, schedule, construction, production, maintenance and safety are
improved.
- It gives a liberal maintenance access road under the center of the
piperack.
- Outside of the support columns, the outriggers give extra piperack
space.
- The deck gives weather protection and improved productivity for operations.
- The deck is also a firebreak between the piping and the equipment on
the deck.
- With this wide area of access, exchanger bundles can be cleaned or
pulled into the covered area. With the dirty end of the exchangers over
the oily water sewer, the piping is shortened and the oily water sewer
is in straight line.
- The precast deck is used for items that require elevation. Often these
items that require elevation are designed with separate structures alongside
of the piperack; these structures limit access. The piping to items on
the deck is generally shorter.
- The deck covers the full width and length of the piperack in the process
area and also serves to support pipes as they enter or leave the rack by
rod hangers.
- The deck also serves for mounting and access to control valves, relief
valves, orifice runs, air coolers, etc.
- Equipment on the deck would have support saddles designed to match
the span of the vertical support columns for quarter point design.
- Compressor structures that require overhead cranes and shelter
for operation and maintenance can be designed with an 'A' frame type crane
supported on rails mounted on the concrete tabletop (Fig. 2). This eliminates
the heavy custom-designed steel structure to support a bridge crane. Cantilevered
monolithic extensions from the concrete tabletop will support precast concrete
decking on both sides of the compressors. A lightweight and inexpensive
pre-engineered building can be added to the tabletop structure to give
weather protection.
- Silo structure designed for 12 silos, each mounted on 3 load
cells, should have the load cells directly over the vertical support columns
(Fig. 3). This requires breaking a paradigm that requires support columns
be in a square pattern, and put them in a triangular pattern. The square
pattern required 30-in. beams because the loads were not over the support
columns. The triangular pattern only required 12-in. beams.
Keep its specifications simple so that you can purchase shop
standard equipment. A simple specification would be a blue Cadillac with
four doors and loaded with standard Cadillac extras. A complex specification
would be a Cadillac with three doors, Honda red paint, a Chrysler motor,
a Ford radio and a Rolls Royce transmission. This sounds ridiculous, but
a lot of companies are buying this type of equipment. A performance-type
specification is a good approach. Select good vendors, tell them what you
want to do, but not how to do it. One vendor told me that if clients would
buy on the performance specification, he could deliver a shop standard
unit faster, with a better guarantee. It would be a better unit and cost
half as much as the complex specification item. This same vendor felt that
many API specifications are an overkill put together by specialists and
consultants with self protection as their goal.
(Click to enlarge.)
Keep
it shop standard can only be accomplished when the
specification is simple. The rewards for buying shop standard
are substantial. When a supplier is asked to deviate from
his standard, it costs more, takes longer, is a custom-designed
item, may be the first of a kind and may carry a lesser
guarantee because of it. It is no longer the comfortable
tried-and-true unit. The owner may think he is buying
a better unit but he may be buying a problem instead.
Keep its standards simple, because like the specifications in
use today, so many standards are outdated and labor intensive. The major
equipment for most projects is only about 25% of total installed cost.
That leaves 75% subject to "designing for constructability" savings.
Some standards to look at are piperacks, platforms, stairs, sewers and
block valves.
- Piperacks have been discussed under structures. The standard
for piperack bents, designed for constructability, is more like modern
highway technology (Fig. 4). Bents are poured horizontally on the ground
using standard forms. They are then stood up in an empty excavation. The
foundation is poured around them. There are no anchor bolts or base plates.
There are metal imbedments in the top of horizontal members for pipe supports
and guides and unistruct in the bottom for lighting, sprinklers, etc. Unistructs
may also be put in the columns for junction boxes, utility stations and
miscellaneous items. There are many details to this design, but the main
obstacle is paradigms.
(Click to enlarge.)
- Platformrequirements are based on the orientation of' manways and nozzles (Fig. 5). Often manways and nozzles seem
to be located where there is room to write on the
orientation plan. When the orientation of each nozzle
was reviewed by all interested people, they could
be all be located on one side of the column or vertical
vessel. This made it possible to have rectangular
platforms and not circular platforms, which one contractor
estimates at 2.5 times the cost of rectangular ones.
These columns have a vertical piperack running up
the column on the platform and piperack side if there
are no air coolers. When there are air coolers, it
is too hot on the piperack side for platforms and
ladders so they must be on the far side.
- Stairs can be simplified by standardizing distances between
all operating and maintenance floors, platforms. catwalks, stair landings
and all walking surfaces (Fig. 6) These increments are proposed as 24 in.
so that three 8-in. stair risers or two 12-in. ladder rungs are equal to
24 in. The treads are proposed as 10 in., which gives a good safe angle.
It is more important that they are all the same so that the angle of stringers
and handrails are all the same This standard is important for shop fabrication,
but even more so when local field labor is used.
- Sewers also follow the straight and simple concept. A precast
concrete trench for storm water runs under the piperack's cantilevered
extensions. The oily water sewer system is a straight pipeline inside of
the precast concrete storm water trench. This design satisfies double containment
requirements by installing sensing elements in the storm water trench.
It also leaves the oily water sewer system exposed, when trench cover is
removed, for inspection because it is not buried. Neither the storm nor
the oily water sewer is sloped. They depend on head and also flow in both
directions to catch basins at both ends of the process unit. Pumps are
lined up along the oily water sewer. This concept is to bring pump to sewer
Don't take the sewer to the pump.
(Click to enlarge.) - Block
valves sizing is a big dollar item (Fig. 7). This
applies to control valves, pumps, traps and relief
valves. Control valves stations can be treated as
a sub-assembly and shipped complete with or without
the control valve positioned above its working position
and held in place by through-bolts. These bolts also
hold a straight piece of pipe between the matching
flanges of the block valves. The straight piece of
pipe (no flanges) is used for flushing and testing.
It is then discarded and the control valve is lowered
into place. To make this design work, there are two
sizes required--line size and control-valve body size.
The control-valve trim size can come later. The line
size is usually the first to be known, and often the
block valves are ordered on line size basis. A valve
twice the size costs about four times the price. Once
sizes are known, you can order control valves, block
valves, bypass valves, reducing ells and flanges.
All valves and flanges will be the same size. Block
valves need to be full port. Reducing ells are used
to go from line size to valve size. Buying an ell
and a reducer and making three welds in lieu of a
reducing ell and two welds is not designing for constructability.
This block valve sizing concept was estimated as saving
$10 million on one large project.
Keep it same size is following the "cookie cutter"
design concept. This does not necessarily mean an industry., standard size,
but more of a project same size. This was vividly brought to mind on a
project with a large and long piperack. In a sincere effort to save money,
the steel was designed very exactly so that there were very many sizes
of' both vertical and horizontal steel members. The standard called for
2-in. fireproofing to be formed and poured after steel erection. The steel
fabricator complained about the many sizes. He fabricated and delivered
to site, all members of one size before going to the next size. The fireproofing
contractor complained because of the many nonstandard forms required to
do his work. The electrical contractor complained because he was held up
waiting for the fireproofing contractor to finish. Because o[* scheduling,
bonuses and penalties, this very complex-designed project ended with several
multimillion-dollar law suits.
Keep it square and squatty. Square (including rectangular) is
to emphasize the extra cost of odd shaped buildings, foundations, platforms
and many other items (Fig. 8 i. Squatty is to emphasize the cost of building
things higher than they need to be. particularly in earthquake zones. A
structure twice as high isn't twice the cost. It is more like Four times
the cost.
- NPSH often determines how high a structure needs to be. However,
contingencies on top of contingencies have been found to add considerable
cost to structures. The real situation may have the normal liquid level
several feet above the outlet. The custom of calculating NPSH requirements
with many contingencies costs a lot of money. An item-by-item review of
a project resulted in the lowering of a complete process unit by 15 ft.
The NPSH required for the most, critical pump was found to be less than
half of the NPSH available.
(Click to enlarge.)
- Control
buildings can be designed based on the square
and squatty design concept. This example is based
on a two story design (which doesn't sound squatty),
but it was the same overall height as the conventional
one-story design it replaced. The one story design
started with a slab on grade. There was a computer
floor space. Then the rackroom and control room with
a false ceiling. Then there was a 6-ft space above
the ceiling for air conditioning ducts and lighting.
The two-story started with the finished floor at grade.
There was no computer floor as with the control room
on the second floor and the rack room directly below
there is no need for a computer floor. The power and
instrument cables entered the building near the ceiling
of the ground floor. The instrument cables feed into
the top of the racks and also exit from the top. They
then penetrate the floor at any point to feed the
consoles. The control building structure was built
using precast double "TT" design. They were
used for the second floor, the roof and exterior walls.
This makes a fast low-cost shell that is also an acceptable
"blast resistant" building. This design
also eliminates the false ceilings and simplifies
the lighting and air conditioning. I call this "parking
garage construction." Fluorescent lighting is
mounted directly underside of the double "TT"
floor and roof. Conduit and junction boxes are on
top of the double "TT"s and are then buried
in the concrete second floor and roof. Air conditioning
ducts are large rectangular soffit type design and
mounted on the walls. Distribution is controlled by
thermostatically operated outlet dampers rather than
duct size. Two side-by-side offices can have several
degrees differential to suit the comfort of individuals.
Keep its support simple is a good example of
how little things that are repeated many times become
big costs. "T" supports for pipes and conduits
that run to the far end of heat exchangers can be mostly
eliminated when the exchangers are turned 180 so that
"T" supports are not required. Supports for
lights, start-stop switches, conduit, junction boxes
and sprinklers are already in place when unistructs
are cast into the precast concrete piperack bents. With
mat type foundations, no adjustable pipe supports are
required as everything is on the same base. Flair headers
can be used as structural members to carry the smaller
pipes required for the flair. A project used a 72-in.-dia.
flair header as a support for the small lines and a
cable tray/walkway. The spacing of supports was 100
ft. Pump supports can be simple double nutted studs,
with no concrete as discussed above. Centrifugal compressors
have been mounted on spring supports with no anchor
bolts and proved to be quieter. That was also the way
they were tested in the fabrication shop.
Keep its schedule sacred. Do not change the schedule
every time there is a problem. Many projects change
the schedule whenever they think there is a justifiable
reason to change. But that doesn't change committment
for sale of the product. Real project management does
all it can to find a way to recover the lost time from
unexpected causes of delays. They bank their reputation
on their solutions.
Keep it site-suitable means considering the unique
conditions of the precise location of the project. I
have seen winterizing for plants on the equator; plans
for importing items to countries that do not allow those
items to be imported; toilets designed for the west,
but installed in the middle east; projects designed
with maximum modules for places that require maximum
local labor; and drawings using English units for places
that only use metric. Be aware of local customs, weather,
labor availability, material availability, etc.
Ten commandments. Following the ten commandments
of KISS design leads to a better managed and less expensive
project. They are also a stimulus for creativity. Use
them to free yourself from design stereotypes and ruts. |
|